Edsel Ford High was built in 1955 on 49 acres of land.
Under the 2026 transformational bond, Edsel Ford would be completely renovated. Estimated cost: $70.7 million
Phase 1 (Years one to five)
- Create secured office/vestibule
- Restroom renovations
- Selective athletic improvements
- Technology and furniture upgrades
Phase 3 (Years 10 to 15)
- Academic spaces renovations
- Auditorium upgrades
- Steam system replacement to HVAC
- Electrical replacement
- Window replacement
- Roofing replacement
- Elevator replacement
- Athletics work including competition field improvements, pool upgrades and locker room upgrades
- Site Improvements including parking/sidewalks/driveways
- Storm water management
Learn more about the 2026 transformational bond on the district website.